Coating has handed over the coated pipes for Tho Trang project

11/10/2013

Coating has handed over the coated pipes for Tho Trang project


Since April 1st 2013, PV Coating has hand over the coated pipes of Tho Trang project for project investor, Vietsovpetro. Total contract value is more than $2 million.

During the 20 days (from Mar 8th – Mar 28th 2013), PV Coating has completed 7.5 km of 10” pipes with different materials such as FBE, PUF, HDPP, CWC and installated anodes in compliance with required quality, technical standards as committed to investors.

Before that, PV Coating has completed projects for Vietsovpetro as: RTC1-BK14, GTC1-RTC1, RC-5 & RC-6 and RC3-RC6 & RC7-RP1.